Sohar Aluminum L L C – Oman

  • 80T Tilting Holding Aluminum Furnace – Demolition & Relining.
  • Location -Cast House(Furnace A,B,C &D)
  • Period Dec 2018 – May 2019
  • ABF Crossover Relining
  • Location – Anode Baking Furnace(East & West)
  • Period March 2019
  • Metal Crucible Relining 7-10 Ton Capacity – Demolition & Relining
  • Location – Cast House(Crucible Workshop)
  • Maintenance Contract – April 2018 to Present
  • Anode Rodding Shop(RS) Ladles 1 & 2 – Demolition & Relining
  • Location – Anode Roding Shop
  • Period – August 2019
  • Induction Furnace (1, 2 & 3) – Repair
  • Location – Anode Roding Shop
  • Period – 2019-2024

CROSSOVER

INDUCTION FURNACE & LAUNDERS

CRUCIBLE

    • ABF Flue Wall Replacement

             – Location –  Anode Baking

             – Period February 2021 to December 2023

    • Reduction

         – Pot Delining & Relining

         – Super Structure Repair

         – Cathode Sealing

         – Material Segregation & Waste Management

         – Location –  Reduction

         – Period October 2021 to March 2024

    • Aluminum Furnace Casting Launder Replacement

         – Location –  Cast House(Crucible Workshop)

         – Period – 2022 – Present

ABF RELINING

POT DELINING & RELINING

Oman Aluminum Rolling Company (OARC) – Oman

  • 70T Tilting Holding Aluminum Furnace – Demolition & Relining.
  • Location – Cast House(Furnace 1,2,3 & 4)
  • Material Supplier : Vesuvius
  • Period April 2018 – May 2018
  • Full maintenance until present
  • 120 Ton New Tilting Holding Aluminum Furnace – Installation.
  • Civil Construction – Foundation, Shed & Refractory Lining
  • Location – Cast House
  • Material Supplier : Vesuvius
  • Period November 2018 – July 2019
  • Floor Concreting 900 sqm – Civil construction.
  • Location – Scrap metal storage area
  • Material Supplier: OPCP(Oman Portuguese cement products LLC)
  • Period June 2019 – July 2019
  • Floor Concreting 369 sqm – Civil construction.
  • Location – Aluminum rolling mill area
  • Material Supplier : OPCP(Oman Portuguese cement products LLC)
  • Period August 2019 – September 2019

TILTING HOLDING FURNACE OARC

OARC CIVIL WORK

OAC Project Images

Strategic and Precious Metal Processing(FCZ) LLC (SPMP)

    • TRF (1,2&3) – Demolition & Relining.
    • Location – CF Building
    • Period from 2020 till present, Relining every 6 months of operation.
    • Rotary Kiln & Discharge Chamber – Demolition & Relining
    • Location – HTF
    • Period June 2020 & 2021 shutdown.
    • New Twin Cyclones – Installation.
    • Location – Dry Gas.
    • Period June – July 2021
    • Rotary Kiln – Demolition & Relining
    • Location – HTF
    • Period June – July 2022 shutdown.
    • RF 1 & RF 2 – Demolition & Relining
    • Location – RF Building
    • Period June – July 2020 Till 2022 – shutdown
    • RC 1 & RC 2 – Demolition & Relining
    • Location – RF Building
    • Period June – July 2020 Till 2022 – shutdown
    • Refractory Maintenance
    • Location – Maintenance Dept(All area)
    • Maintenance Contract 2020 till Present

SPMP

Vale Oman Pelletizing Plant(VALE)

    • Line A, Line B & RMP Area
    • Location – Rotary Kiln, Annular Cooler, Travelling Grates, Cyclones & Grinding mill.
    • Supervision team, Contractor management, Planning & Schedule preparation for CSD, Operational Procedure(Pro) & Job Safety Analysis (JSA) preparation.
    • Maintenance installation Specialist 2020-2024