Sohar Aluminum L L C – Oman
- 80T Tilting Holding Aluminum Furnace – Demolition & Relining.
- Location -Cast House(Furnace A,B,C &D)
- Period Dec 2018 – May 2019
- ABF Crossover Relining
- Location – Anode Baking Furnace(East & West)
- Period March 2019
- Metal Crucible Relining 7-10 Ton Capacity – Demolition & Relining
- Location – Cast House(Crucible Workshop)
- Maintenance Contract – April 2018 to Present
- Anode Rodding Shop(RS) Ladles 1 & 2 – Demolition & Relining
- Location – Anode Roding Shop
- Period – August 2019
- Induction Furnace (1, 2 & 3) – Repair
- Location – Anode Roding Shop
- Period – 2019-2024
CROSSOVER






INDUCTION FURNACE & LAUNDERS


CRUCIBLE

- ABF Flue Wall Replacement
– Location – Anode Baking
– Period February 2021 to December 2023
- Reduction
– Pot Delining & Relining
– Super Structure Repair
– Cathode Sealing
– Material Segregation & Waste Management
– Location – Reduction
– Period October 2021 to March 2024
- Aluminum Furnace Casting Launder Replacement
– Location – Cast House(Crucible Workshop)
– Period – 2022 – Present


POT DELINING & RELINING

Oman Aluminum Rolling Company (OARC) – Oman
- 70T Tilting Holding Aluminum Furnace – Demolition & Relining.
- Location – Cast House(Furnace 1,2,3 & 4)
- Material Supplier : Vesuvius
- Period April 2018 – May 2018
- Full maintenance until present
- 120 Ton New Tilting Holding Aluminum Furnace – Installation.
- Civil Construction – Foundation, Shed & Refractory Lining
- Location – Cast House
- Material Supplier : Vesuvius
- Period November 2018 – July 2019
- Floor Concreting 900 sqm – Civil construction.
- Location – Scrap metal storage area
- Material Supplier: OPCP(Oman Portuguese cement products LLC)
- Period June 2019 – July 2019
- Floor Concreting 369 sqm – Civil construction.
- Location – Aluminum rolling mill area
- Material Supplier : OPCP(Oman Portuguese cement products LLC)
- Period August 2019 – September 2019
TILTING HOLDING FURNACE OARC






OARC CIVIL WORK








OAC Project Images













Strategic and Precious Metal Processing(FCZ) LLC (SPMP)
- TRF (1,2&3) – Demolition & Relining.
- Location – CF Building
- Period from 2020 till present, Relining every 6 months of operation.
- Rotary Kiln & Discharge Chamber – Demolition & Relining
- Location – HTF
- Period June 2020 & 2021 shutdown.
- New Twin Cyclones – Installation.
- Location – Dry Gas.
- Period June – July 2021
- Rotary Kiln – Demolition & Relining
- Location – HTF
- Period June – July 2022 shutdown.
- RF 1 & RF 2 – Demolition & Relining
- Location – RF Building
- Period June – July 2020 Till 2022 – shutdown
- RC 1 & RC 2 – Demolition & Relining
- Location – RF Building
- Period June – July 2020 Till 2022 – shutdown
- Refractory Maintenance
- Location – Maintenance Dept(All area)
- Maintenance Contract 2020 till Present



SPMP

Vale Oman Pelletizing Plant(VALE)
Line A, Line B & RMP Area
Location – Rotary Kiln, Annular Cooler, Travelling Grates, Cyclones & Grinding mill.
Supervision team, Contractor management, Planning & Schedule preparation for CSD, Operational Procedure(Pro) & Job Safety Analysis (JSA) preparation.
Maintenance installation Specialist 2020-2024






DRY OUT